International Broadcast Center, FIFA World Cup

Building use
Broadcast facility
Floor area
About 300,000 sq ft
Status
Complete
Structural system
All light-gauge (cold-formed) steel, no red iron

Mythic's role and scope

Structural engineer of record (SEOR)

Engineering challenge

A very large temporary broadcast facility on a fixed event schedule.

Solution

An all light-gauge steel structure with no red iron.

Documented results

About 300,000 sq ft built in about 4 months, and taken down in under a month.

Project photos